United States v. William Cramp & Sons Ship & Engine Building Co.

1907-05-13
Share:

Headline: Contractor’s broad final release upheld, barring more than $500,000 in claims; Court reversed the lower court and ordered judgment for the United States, enforcing the contract’s closing release.

Holding: The Court held that the contractor’s May 18, 1896 final release, executed as required by the contract, settled all claims arising under or by virtue of the contract and bars the later suit.

Real World Impact:
  • Prevents contractors from suing on claims covered by broad contract releases.
  • Allows the Government to close out large contracts without reopening settled matters.
  • Reinforces the finality of contract-form releases approved by officials.
Topics: contract disputes, final releases, government contracts, contractor claims

Summary

Background

A private building company contracted with the Government to construct a vessel for more than $3,000,000. The contract required a final payment only after the company executed a release in a form approved by the Secretary of the Navy. On May 18, 1896, after delivery and acceptance, the company signed a sealed release that used broad language, including a clause to "remise, release and forever discharge" the United States "of and from all and all manner of debts ... claims and demands whatsoever, in law or in equity, for or by reason of or on account of the construction of said vessel under the contract aforesaid." Over a year later, the company sued for claims totaling more than $500,000 and obtained a judgment in the Court of Claims.

Reasoning

The central question was whether the May 18, 1896 release covered claims that grew out of the contract but were not strictly about the physical act of building—such as delay claims. The Court looked to the contract language that required a final release and to the release’s broad wording. It concluded the phrase "by virtue of" or "by reason of" the contract clearly included claims arising from performance, including delays tied to construction. Because the release was the contractually required instrument, sealed, and supported by the contract as consideration, the Court refused a narrow technical reading and held the release settled all disputes.

Real world impact

The practical result is that the Government prevailed: the Supreme Court reversed the Court of Claims and remanded with instructions to enter judgment for the United States. The decision enforces comprehensive final releases negotiated and approved under a contract, meaning contractors who sign such releases will have limited ability to reopen settled claims. The Court also noted the suit was brought more than a year after the release, underscoring the release’s finality.

Ask about this case

Ask questions about the entire case, including all opinions (majority, concurrences, dissents).

What was the Court's main decision and reasoning?

How did the dissenting opinions differ from the majority?

What are the practical implications of this ruling?

Related Cases